Reference architecture

Requirements-to-Verification Reference Architecture

A requirement, a test definition, an execution and an accepted result are different engineering records and decisions. Structure their relationships so a reviewer can understand what was checked and what still needs assessment.

Published by AroTrace · Architecture version: 1.0

What is a requirements-to-verification architecture?

A requirements-to-verification architecture defines how requirement intent, implementation work, test definitions, executions and results relate across responsible systems. It keeps a planned check separate from its execution and a recorded outcome separate from engineering acceptance. Source identity and available version or configuration context help reviewers assess the evidence. The architecture selects links and data movement for the actual workflow; it does not assume every connector supports a complete lifecycle baseline.

Reference diagram

Distinct relationships for requirement implementation, planned verification, test execution, results and human assessment.

  • Development workRelationship: Implements Requirement
  • RequirementRelationship: Intended to be verified by Test case
  • Test executionRelationship: Executes Test case
  • Test executionWorkflow / event: Produces an outcome Result / evidence context
  • Result and requirement contextContext access: Assesses acceptance Engineering reviewer
  • Azure DevOps run / resultsSynchronization: AroTrace: cases synchronized first Mapped Codebeamer test context
Conceptual verification relationships. These rows are not a mandatory sequence of copies or a claim that every object and edge is supported by every connector.
Download architecture diagram (SVG)

Architecture objective

The purpose is to make a verification decision understandable. A linked test case says what should be checked. A test execution records an attempt, and its result records an outcome. A reviewer still determines whether that outcome is adequate for the requirement.

Define the test context, result location and responsible reviewer before choosing an information flow. The Codebeamer–Azure DevOps example below shows one documented execution path within this broader model.

Systems and responsibilities

Source-of-truth and decision boundaries
ComponentResponsibilitySource of truth / owner
Requirements systemRequirement intent and applicable revisionRequirements owner
Development systemImplementation and delivery stateDevelopment owner
Test environmentTest definition, execution and recorded outcomeVerification owner
AroTraceConfigured relationships and selected transfersSource systems retain domain records
ReviewerEvidence adequacy and acceptance decisionEngineering process owner

Integration patterns

Relationships: Separate “implements”, “intended verification” and “executes” semantics. A relationship records context, not proof of correctness.

Execution synchronization: In the documented ADO → Codebeamer flow, referenced test cases must already be synchronized before runs/results enter mapped Codebeamer context. If a referenced case is not mapped, the run is skipped.

Context and review: Identify the tested version or configuration where available. Agree what evidence a reviewer needs and verify that the selected source systems expose it.

Relationship model

  • Development item → implements → requirement.
  • Requirement → intended to be verified by → test case.
  • Execution → executes → test case; execution → produces → result.
  • Engineering review evaluates the result against the requirement and acceptance criteria.

A change scenario

  • A requirement changes after a test execution.
  • A direct relationship configured for suspect tracking can be flagged.
  • The reviewer examines available requirement and test context.
  • The verification owner decides whether the old result remains relevant or another execution is needed.
  • The relationship is explicitly confirmed or corrected; a flag does not automatically rerun tests or invalidate every result.

Failure and exception boundaries

A missing synchronized test-case mapping prevents the documented ADO run from being imported. That is different from a failed test outcome: missing connectivity must not be presented as evidence that the requirement passed or failed.

  • Unavailable test system: identify stale or incomplete evidence before accepting it.
  • Expired Test Management access: verify access and mappings with the responsible administrator.
  • Changed test mapping: reconcile case identity before relying on execution references.
  • Deleted test case: decide how historical evidence and unresolved references are handled.
  • Conflicting result context: preserve the distinction between transfer success, test outcome and acceptance.

Security and governance considerations

Grant only required test-management and target-write access. Keep evidence interpretation with qualified reviewers. Establish which roles can change requirements, publish test results and approve acceptance. Verify the exact permission and provenance behavior of the chosen integration rather than assuming a link supplies it.

Example implementation paths

Codebeamer–Azure DevOps is the documented run/result synchronization example. Codebeamer–GitLab is a separate integration evaluation path, not evidence that the same test-execution behavior applies. Test-case generation is a different workflow from executed verification.

When this architecture fits

Use this pattern when requirements, implementation and test evidence are distributed and an engineer needs a defensible account of their relationships.

When another approach may be sufficient

It may add little where the complete verification process and required evidence are already governed within one platform, or an existing integration covers the full evaluated flow.

Questions about this approach

Is a passing test result proof of requirement satisfaction?

Not on its own. Review test adequacy, applicable requirement revision, tested configuration and acceptance criteria.

Does this architecture require synchronization of every record?

No. Choose synchronization where a working representation is needed, and configured relationships for independently maintained records.